Progress & Burn-up
Every milestone shows how far along it is: a progress pill in the Milestones view, the Current Milestone section on the dashboard, and xpo milestone show.
What counts
- Only issues without children. An epic's progress is its sub-issues, so the epic itself isn't counted twice.
- Canceled and duplicate issues leave the scope. They don't count as done or as remaining.
- Unestimated issues count as 1 point, the same as the backlog's group headers.
Issues or story points
The progress pill shows issues done (4/7). Click it to switch every milestone to story points done. The choice is kept in this browser. Hovering the pill shows the status breakdown in the pill's unit, a time bar to the target date, and the burn-up.
The burn-up chart
The burn-up starts on the day the milestone became Current. Done work rises toward the dashed scope line. Adding work while the milestone is in progress moves only the scope line, so you can see scope creep instead of a burndown that never reaches zero.
The chart counts what the pill counts: issues, or story points.
- Order (the default) draws one evenly spaced step for each change to the scope or the done work. A milestone finished in an afternoon still shows every step.
- Time draws one point per day.
Switch between them with Order | Time, right of the legend, on the dashboard and on completed milestones. The choice is kept in this browser.
Hovering a step shows when it happened and what changed: done, reopened, added, removed, canceled or estimated. Completing a milestone, or moving an epic with its children, is one step. Changes before any issue is done fold into the first step.
From the CLI and API
xpo milestone show @current # counts, story points, issues
xpo milestone show @current --json # counts by status, total, done, points {total, done}
GET /api/milestones/{ref}/progress returns the burn-up data: steps (Order) and days (Time), both with point sums. A completed milestone keeps its final counts and story points.